lcn wiring instructions

RELATED FAQS

Question
Answer
When installing the arm; the gearbox shaft and door must be at the (+90°) full open position. The following step are used to install the Senior Swing (STD) pull arm. Install the header using app...
The 4600 hold open switch (for the new 1-24 single terminal strip I/O board) wires into terminals 2 and 6 or 4 and 6.
Closers mounted according to LCN installation instructions require no periodic maintenance or seasonal adjustments.  Monthly, quarterly, and annual visual inspections are recommended for Fire/...
There are 2 wiring diagrams for sequencing a double door vestibule application shown on page 13 of the 4630/4640 installation instructions.
The 4630/4630 operator has a 12 VDC and 24 VDC output that can power an electric strike or maglock. The wiring diagrams are shown on page 14 of the installation instructions (attached). 4600 Insta...
The ES Filter started to ship with these units (Senior Swing/Benchmark/Falcon) on 4/22/2013.  The ES Filter kit will help eliminate line noise from an Electric Strike if used. 
On the Senior Swing, if you have line noise from a strike the unit will go into an Error Code on the Control Box (Er14) and will not operate.  Adding the ES Filter, which is a diode, will eliminate...
On the Benchmark and Falcon, if there is line noise from a strike then the unit will lose it's hold open time.  Adding the ES Filter, which is a diode, will resolve this issue and the unit will hol...
The Benchmark III control has a 24VDC, 2.5 amp power supply, and built in relay for controlling electric strikes or other accessories less than 2.5 amps current load. For a fail secure strike, r...
The programming processes for Allegion devices can be both product and features specific.  Some products programming processes are electronic in nature, others are physical in nature. &nbs...
The current (digital control box) activation input wiring harness (# 761464-00) is included in the Sr. Swing parts bag (-518), and has 4 wires in it, Black, White, Yellow, & Gray. This harness p...
When installing the arm; the gearbox shaft  and door must be at the (+90°) full open position. The following step are used to install the Sr. Swing (REG) push arm. Install the header and door brac...