Excessive premature frame rusting is caused by improper jobsite installation practices and most likely caused by the following circumstances:
Grout:
Frames are grouted in place using incorrec...
During the construction cycle, spot rust is usually attributed to either material handling damage or improper storage of the material on the jobsite. The material must be repaired and repainted as ...
CAUTION must be used in investigating this problem - In most cases, excessive field rusting of products is caused by improper storage at the jobsite. That situation must be validated prior to refus...
Yes, an additional jamb anchor can be used at the bottom of the frame in lieu of the typical (adjustable or weld-in) base anchor in fire rated frames.
This is limited to the anchor designed for...